Planned wired network upgrade, June 8th through to June 12th

as of Wedesday PM

Work is progressing across college, but to prioritise students living in the engineers have fallen behind slightly, this version of the plan shows where we have got to and where we have moved work highlighted with a red background.

We have managed to keep each building downtime to just over 1 hour, with one exception where we had an issues overnight.

Our Lodge Manager and Estates Manager will be managing the physical site access for our engineers, with myself and Abs assisting with the configuration and testing of the new kit.

Any questions as ever please do get in touch via email to ict.desk@some.ox.ac.uk.