We now have an agreed schedule of work by our suppliers (LAN3) to work on the new College wireless network.
Our suppliers are planning on working on the wireless network within College starting on 9th October fitting new equipment to each room in the ROQ buildings, moving on to the rest of the site from the 11th, and finishing on 31st October.
This work will require access to buildings and rooms on the dates given above, the College will email out a reminder a few days before work commences to all.
The full schedule is available here:
Schedule: | Dates |
ROQ East & West | 09/10/17 – |
On site configuration & knowledge transfer | 11/10/17 – 13/10/17 |
Radcliffe House | 11/10/2017 |
Margery Fry House | 11/10/2017- 13/10/2017 |
Dorothy Hodgkin Quad & MTC | 17/10/2017 |
155 Woodstock Road | 17/10/2017 |
Library One AP still to install |
20/10/2017 |
Barbara Craig House | 26/10/2017 |
Maitland | 20/10/2017 |
Dining Hall including PDR/SCR/Reading Room/Staff Room/Offices | 24/10/2017 |
House | 20/10/2017 |
Hostel / Bursary | 23/10/2017 |
119a / Nursery | 24/10/2017 |
West Lodge | 23/10/2017 |
Vaughan | 25/10/2017 26/10/2017 |
Holtby | 25/10/2017 26/10/2017 |
Penrose & Wolfson including FAH & BWR Configuration still ongoing |
30/10/2017 |
Darbishire Quad, Lodge House & NCR Configuration still ongoing |
30/10/2017 |
Park | 31/10/2017 |
Final configuration day | tbc |
Red = behind schedule, some issues with connectivity
Amber = work ongoing, expect connectivity issues
Green = complete
If you have any questions or concerns please do get in touch via ict.desk@some.ox.ac.uk or call 01865 2 70597.