During this summer period, we are adding a lot more access points to every building for better reliability and redundancy in the Wi-Fi network, this work will have less downtime in the network during this period, but there may be more onsite disruption, due to cabling work. The timetable below shows what buildings are being worked on each week during this 2025 summer period.
The days buildings being worked on | Which Building | Where can you work without disruption? | Completed? |
---|---|---|---|
11th – 27th August | Vaughan | ||
11th – 19th August | Maitland | ||
Library/Holtby | |||
House | |||
Vaughan | |||
20th August – 2nd September | Catherine Hughes Building + Bedford House | Library | |
20th August – 4th September | Dorothy Hodgkin Quad + Margaret Thatcher Centre + Radcliffe House | Library | |
26th August – 8th September | Wolfson | Library | |
28th August – 9th September | Park Building | Library | |
3rd September – 11th September | ROQ West | Library | |
5th September – 17th September | Margery Fry House | Library | |
8th September – 22nd September | Darbishire | Library | |
10th September – 26th September | Penrose Building | Library | |
12th September – 17th September | ROQ East | Library | |
18th September – 23rd September | Hostel + Bursary | Library | |
18th September – 23rd September | 155 Woodstock Road | On site in the college Library | |
23rd September – 26th September | Dining Hall and SCR | Library | |
24th September – 26th September | Barbara Craig House | Library | |
Dates to be confirmed | Nursery |
If you have any questions or concerns about the ongoing work over the summer period, please contact us on ict.desk@some.ox.ac.uk or give us a call on 01865 270597