During the summer vacation, we are increasing our network coverage across the College by adding more access points to every building. This work should have no downtime for the network, but there will be onsite disruption, due to drilling and building works.
To reduce inconvenience to our members we have liaised closely with the Estates Manager (Steve Johnson) and his team to schedule the work required to install the new cabling and wireless Access Points at the same time as other building work has been scheduled. This should reduce the amount of work the network project will be undertaking in actively used buildings.
The timetable below shows which buildings the project will be installing our new Access Points into during August/September along with alternate work locations and further information, some details are yet to be confirmed but we will keep this page updated as we go.
The days buildings are Free | Which Building | Alternate Work Location | Occupied or Not | Completed? | Notes |
---|---|---|---|---|---|
11th Aug – 7th Sep | Maitland | Notice to Building Occupants | Completed | 85% complete. return 26th Aug – 28th Aug | |
11th Aug – 29th Aug | Library | Notice to Building Occupants | In progress | ||
11th Aug – 5th Sept | House | CHB Group Study Room | Notice to building Occupants | Completed | Complex routes causing issues, delayed |
18th Aug – 26th Sept | Holtby | Not Occupied | Completed 22/08 | ||
26th Aug – 2nd Sept | ROQ West | Notice to Building Occupants | Completed | ||
26th Aug – 28th Aug | Nursery Cabinet installation and cable pull | Not Occupied | Completed | ||
20th Aug – 22nd Aug | Nursery | Not Occupied | Completed 22/08 | ||
26th Aug | West Lodge | Notice to Building Occupants | |||
1st Sept – 15th Sept | Vaughan | Not Occupied | In progress | ||
1st Sep – 5th Sep | Radcliffe House | Not Occupied | Completed | ||
3rd Sep – 16th Sep | Darbishire | TBC | Notice to Building Occupants | ||
3rd Sep – 12th Sep | Wolfson | Not Occupied Apart from FAH | |||
16th Sep – 19th Sep | ROQ East | Notice to Building Occupants | In progress | ||
15th Sep – 18th Sep | Hostel and Bursary | TBC | Notice to Building Occupants | In progress | |
17th Sept – 26th Sept | Park Building | Not Occupied | |||
22nd Sep – 23rd Sep | 155 Woodstock Road | Notice to Building Occupants | |||
22nd Sep – 26th Sep | DHQ – MTC | Not Occupied | |||
22nd Sep – 26th Sep | Barbara Craig House | Not Occupied | |||
TBC | M-FRY | ||||
TBC | Penrose | ||||
TBC | CHB + Bedford House | ||||
TBC | Dining Hall + SCR |
If you have any questions or concerns about the ongoing work over the summer period, please contact us on ict.desk@some.ox.ac.uk or give us a call on 01865 270597